Comment: Migrated to Confluence 5.3

...

Then there is 1 week we call the release-week. The release week starts on the code freeze day.  On the morning after the code freeze day, a tag is created for the release.  It is assumed that all coding work has been completed by that time, but practice learns that this should be checked with the group ;-)  After the versions are updated on the branch, we start with pointing the continuous integration jobs to the branch and start smoke testing.  Once that is OK, the publishing of the release can begin.

Dates

This calendar shows the release dates and also JIRA Freeze and Code Freeze dates for the releases.

Issue tracker

See the Activiti project in the codehaus JIRA

...