This document lays out the development priorities and plans for the GumTree software version 1.7. The aim of this plan is to provide an overview of works that are committed in the current development iteration cycle. This is a living document and is subject to change based on the project priority.

Release Schedule

Phase

Start

End

Duration

Release

Planning

17th October 2011

21st October 2011

1 week

 

Iteration 0

24th October 2011

18th November 2011

4 week

1.7.0

Iteration 1

21st November 2011

20th January 2012

9 week

1.7.1

Iteration 2

23rd January 2012

10th February 2012

3 week

1.7.2

Iteration 3

13th February 2012

2nd March 2012

3 week

1.7.3

Iteration 4

5th March 2012

23rd March 2012

3 week

1.7.4

Endgame

26th March 2012

13th April 2012

3 week

1.7.5

Plan Items

Category

Plan Items

Server Side

  • Authentication in GumTree server
  • Execution engine

Workbench

  • Context aware API

Data Acquisition

  • SICS proxy refactoring
  • New SICS table tree
  • SICS scan framework
  • SICS proxy stability on GumTree server

Data Reduction

  • Deprecate Cicada
  • Replace reduction algorithms with Python scripts

Scripting

  • Release Python script library

NBI

  • Proposal database connectivity
  • Dashboard migration
  • Basic reduction algorithm

Quokka

  • Jython migration

Wombat

  • Release due in Iteration 1

Echidna

  • Release due in Iteration 3

Kowari

  • Release due in Endgame

Documentation

  • High level UML diagrams on GumTree APIs