Introduction

This document lays out the development priorities and plans for the Gumtree software version 1.9. The aim of this plan is to provide an overview of works that are committed in the current development iteration cycle. This is a living document and is subject to change based on the project priority.

Release Schedule

Phase

Start

End

Duration

Release

Planning

01/07/2013

05/07/2013 

1w

 

Iteration 0

08/07/2013

06/09/2013

9w

1.9.0

Iteration 1

09/09/2013

18/10/2013

6w

1.9.1

Iteration 2

21/10/2013

15/11/2013

4w

1.9.2

Iteration 3

18/11/2013

06/12/2013

3w

1.9.3

Iteration 4

09/12/2013

10/01/2014

5w

1.9.4

Endgame

13/01/2014

31/01/2014

3w

1.9.5

Plan Items

Category

Plan Items

Server Side

  • Automatically launch or stop Gumtree server with sync of SICS
  • Migrate all servers to a single host box

Plotting

  • Improve plotting quality
  • Provide more plotting features

SICS Proxy

  • Evaluate Scala language
  • Evaluate Vertex project 
  • Revise interface/message between SICS and Gumtree

Data Reduction

  • Quokka data reduction support
  • Evaluate porting DAVE lib to Gumtree

Scripting

  • Upgrade scripting UI support
  • Improve Python interface for SICS support

Quokka

  • Finalise the product
  • Time estimation project

Kowari

  • Reduction in Python script

Kookaburra

  • Multi-sample workflow

Taipan

  • Static window for live data support
  • Dial widget for detector counts
  • Diffscan & meshscan support

Platform

  • Remove unnecessary dependencies

Future Plan

  • White paper for Gumtree 2.0

 